Scope of Work:

  • Removal of two 10,000 and 3,000 BBL bolted galvanized salt water storage tanks
  • Installation of a new 10,000 BBL salt water storage tank

Install operations:

  • Installed internal cathodic protection system
  • Installed primary skim pump
  • All mechanical and electrical tie ins

Modifications / Repairs:

  • Sweep-blasted interior of new tank and applied epoxy phenolic interior coating system
  • Re-installed all tank appurtenances including stairway
  • All related site work including re-grading
  • All equipment, materials and construction spoils had to be moved to and from job site with barges due to facility being located on an island
  • All labor had to be boated to the island daily


Download Kinder Morgan Project Profile

TESTIMONIALS
CORPORATE OFFICES

1400 Woodloch Forest Dr. Suite 500
The Woodlands, TX 77380, USA
Phone: 832-299-3200 - Fax: 832-299-3299

57 Old Onondaga Road West
Brantford, ON N3T 5M1, Canada
Phone: 519-756-8222 - Fax: 519-753-1453
Toll Free: 1-877-252-7826



NEWS & MEDIA

  • TF Warren Extends Best Wishes to Intern Amber Warrington

  • Blastco Crew in Hulah, OK First Recipients of the "Site Excellence" Award

  • Tarsco Bolted Tank Can Provide Solutions For All Your Fire Protection Tank Needs

  • Tarsco Exhibiting at NISTM's 10th Annual National Aboveground Storage Tank Conference and Trade Show Sept. 13-14 in Galveston, TX

  • Blastech Mobile Receives ISO 9001 Certificate to the New 2015 Standard

  • 1
  • 2
  • 3
  • 4
  • 5